Morgan Ibbs Group played a key role in the delivery of one of the UK’s largest rapid-only EV charging hubs at Three Maids Hill, Winchester. Delivered in collaboration with Parco Civil Engineering & Groundworks, this flagship project represents a significant step forward in supporting the UK’s transition to electric vehicles and sustainable infrastructure.


The Winchester Super Hub has been designed to provide high-capacity, ultra-rapid charging in a strategic location, enabling efficient and accessible EV charging for the growing number of electric vehicle users.


The challenge >>

Developing a large-scale EV charging hub of this size required:

  • Coordination across multiple contractors and disciplines.
  • Installation of extensive electrical infrastructure within tight timelines.
  • Integration of high-capacity power systems to support ultra-rapid charging.
  • Delivery of robust, future-proofed solutions to meet increasing demand.


The complexity of the project demanded precision, technical expertise, and seamless collaboration between all parties involved.


The outcome >>

The Winchester Super Hub is now fully operational and open to the public, providing one of the largest ultra-rapid EV charging facilities in the UK.


This project demonstrates:

  • The ability to deliver large-scale, high-performance EV infrastructure.
  • Strong collaboration between Morgan Ibbs Group and project partners.
  • A commitment to supporting sustainable transport and energy solutions.
  • Expertise in managing complex electrical installations with precision and efficiency.


The works >>

  • 3km of cable pulls 
  • Installation, termination and testing & inspection of:
  • 44 ultra-rapid EV chargers
  • 2x Battery Energy Storage Systems.
  • Dedicated MCCB panels for EV charging and site services
  • Data network infrastructure 
  • 72x lighting bollards & 6x lighting columns


quotesArtboard 1 copy 2

The scale of this 44-unit ultra-rapid charging hub reflects the ambition behind the UK’s transition to sustainable transport. Seeing our specialist EV team working collaboratively alongside Parco Civil Engineering & Groundworks to successfully deliver such a significant project is a proud moment for Morgan Ibbs Group. This development demonstrates how strong partnerships and technical expertise can help accelerate the journey to net zero. Projects of this scale are only possible through exceptional teamwork and collaboration.

Nathan Morgan - Director

Morgan Ibbs Group

Michael Hand, Parco Civil Engineering & Groundworks with Nathan Morgan, Morgan Ibbs Group.

Conclusion >>

The successful completion of the Winchester EV Super Hub highlights Morgan Ibbs Group’s capability to deliver complex infrastructure projects at scale. By combining technical expertise with collaborative working, the team has helped create a future-ready facility that supports the continued growth of electric vehicles across the UK.



Case studies >>